Optimum Construction Resource in Space, Time and Cost

Chin-Chih Kuo, Ren-Jye Dzeng
Pages 1-6 (2000 Proceedings of the 17th ISARC, Taipei, Taiwan, ISBN 9789570266986, ISSN 2413-5844)
Abstract:

The article summarizes the overall idea of the study and presented the results of the first stage -- "simulation visualized of construction schedule". At present, we have corresponded and combined the CPM network diagram and the 3D object model for dynamic presentation. This kind of 4D dynamic diagram always simulates the 3D outlook at any point of time in the process of simulating project construction in the way of assembling blocks to inquire and obtain the planning of construction resources, status of use and performance of execution and can be displayed according to the change in the construction sequence. The results of the study provide an optimal location for describing the spatial information and resources required for building construction. In addition, this can increase the friendliness and accuracy of the CPM network diagram and can be used for reviewing the problems of hidden constructing conflicts and interface or as the visualized basic document for works like quantity calculation, structure calculation, piping construction and Maintenance.

Keywords: spatial resource, time-cost trade off, geographic information system (GIS), genetic algorithms (GA), 4D dynamic diagram, 3D object model