Abstract:

In 1997, the semi-automatic unified system for piling work was developed and introduced to the market as the 'GRB SYSTEM'. This system is comprised of four distinct machines; the ?Silent Piler?, the ?Unit Runner?, the ?Clamp Crane?, and the ?Pile Runner?. The 'Press-In' method, with its silent and vibration-free driving process, may be the solution to the widespread problem of noise and vibration on construction sites. Also the ?GRB SYSTEM? will bring, not only foundation work, but various other areas of construction into the new technologically-advanced era of construction work.